PPL Service Center

An incredibly complex project, the PPL Service Center project in Harrisburg, PA included over fifteen phases of additions and renovations. The work included several major building additions and approximately eleven interior renovation phases in a fully occupied building. The building had to remain functional for the utility company in the event of a storm response emergency, including all service vehicles. It also remained functional for daily operations through all phases of the work.

Dolan Construction Inc. was awarded the $11,000,000.00, 2 ½ year project and completed each phase per our phasing and budgeting schedule. We experienced numerous interferences with operations due to storm response requirements by the owner but were able to successfully manage through each time and shift work to areas of the building where we were not in the way of important operations for the utility company.